Vince & Lina

Pond Constructions : Vince & Lina


Footings
Reo Between Filter Boxes & Pond
Brickwork & Mesh Support Between Pond & Filters
100ml Floor
Plastering finished
Fibre Glass Nearly Done
Gel Coat & 4 Bottom Drains
3500 L Vortex ready to go in
Connected Pipes from Vortex to Filter Chambers
Chamber No1 is lined with Japmat & Filled with Bio Balls
Chamber No2 Brushes
Chamber No3 has a Stainless Floor & Stainless Strainers for K1
Chamber No3 Up and Running with the K1 & 4 Air Domes
Chamber No4 has Japmatt + 2 x 16000 L Pumps, Has more Japmatt now + UV Light
4 Filter Chambers
There are 6 Jets with each 16000L Pump running 3 Jets
Total of 70,000 L
Still Cosmetics to do



 